Time and cost reduction

REDUCTION OF TIME AND COSTS

METHODOLOGY.

https://www.cestarorossi.it/aggiornato/wp-content/uploads/2022/07/Cestaro-rossi-impianti-2-1200x640.jpg




MEASURE TAKEN TO REDUCE THE



COSTS AND INTERVENTION TIME

Before the start stop

    • Start erection of metal structures of scaffolds at least 30 days before start-up.
    • Presence on site of Supervisors and Coordinators at least 15 days prior to start-up for study of activities to be carried out, organization of work and documentation

During the period of the stop

    • Use of two wash areas where possible
    • Equipment washing performed during the 2nd and 3rd shifts
    • Bolting and filling equipment with water for testing during 2nd and 3rd shifts
    • Use of multispecialty personnel: welders/tubers, switchers/columnists, carpenters/tubers, electricians/instrument makers.