Pre-bid activities

ACTIVITIES CARRIED OUT BEFORE FORMULATING THE BID

DOCUMENT ANALYSIS

  • Analysis of documents received
    Plant type information
  • Refinery layout study
  • List of work to be performed and plant and equipment isolation diagrams
  • Study of equipment layout (elevations, accessibility, particular types of material , etc.).
  • Materials and related technical drawings by equipment, by type, by plan location, by installation elevation

INSPECTION AND CONFIRMATION CHECK

Examination of site conditions

  • Availability of utilities
  • Logistical situation
  • Accessibility to facilities

Availability of materials

Control of possible interference with work performed by other companies

Identification of work to be performed by subcontractors

  • Scaffolding
  • High pressure washes
  • Chemical washes
  • Special lifts
  • Insulations

SITE ORGANIZATION PLANNING

  • Number of area coordinators
  • Number of foremen ( 1/ 10 workers)
  • Equipment and means of work
  • Workforce

Intervention planning based on

  • Stop times set by the customer
  • Technical information
  • Particular interventions planned by the client

Risk analysis