PREPARATORY ACTIVITIES
METHODOLOGY.

SITE MOBILIZATION
- Containers offices
- Box showers and toilets
- Locker rooms and canteen
TRANSFER TO PLANT AREAS
- Gaskets, blind flanges, blind, test rings
- Bolts and tie rods
- Box with equipment (tirfort, slings, wrenches, hydraulic screwdrivers, etc.)
- Dedicated equipment (motorized tube bundle extractors, bundle conveyor machines)
- Crane
- Fork lift
- Compressors and electric generators
- Electro and moto welders

DOCUMENT PREPARATION
Preparation of documents for issuance of work authorization
Meetings with client’s technicians to
- Aspects/definition of work to be performed
- Safety for the performance of the activity
Assembly of metal structures of scaffolds where possible
Bolt lubrication flange couplings
Training meeting of all personnel on the specific hazards of the facilities in which they work
Preparation for each foreman of all documentation related to the work he is assigned to do